Const. of DEG Shed at Tshenkhar Top, KHP Top,Khenthongmani and Yelchen Bhutan Telecom Ltd Contract Awarded
Procurement Category: Civil
Dzongkhag/Location: Samdrup Jongkhar
Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)
Procurement Method: Limited Tendering
Annual Procurement Plan: 2021
Bidding Process: Single Stage Bidding - Single Envelope
Contact Details: Cheki Wangmo 17162638 BTL,SJK
Status: Contract Awarded
Bidding Details
Submission Date: September 07 2026, 12:00 AM
Opening Date: July 06 2021, 02:30 PM
Prebid Date: None
Prebid Place: None
Evaluation Details
Financial Evaluation: 100%
Agency Documents
| Sl | Document | Link |
|---|---|---|
| 1 | Integrity Pact Document | Download |
| 2 | RFP | Download |
Document Prerequisites For Participation
| Sl | Document |
|---|---|
| 1 | Bid Form |
| 2 | CDB License |
| 3 | Integrity Pact Document |
| 4 | Tax Clearance |
| 5 | Trade License |
Tender Items(BOQ/BOM)
| Sl | Item Code | Item Name, Additional Description/Specifications |
UoM | Qty |
|---|---|---|---|---|
| 1 | TshenkharTop | |||
| 2 | EW0105 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Ordinary Soil, | cu.m | 4.7 |
| 3 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.66 |
| 4 | CW0004 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 40 mm nominal size, | cu.m | 0.24 |
| 5 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 88.91 |
| 6 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 1.26 |
| 7 | SW0003 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels, | kg | 223.36 |
| 8 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 15.36 |
| 9 | SW00341 | Providing & fixing CRIL Sheeting with G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses-50mm, | sq.m | 16.48 |
| 10 | KHP Top | |||
| 11 | EW0105 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Ordinary Soil, | cu.m | 4.7 |
| 12 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.66 |
| 13 | CW0004 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 40 mm nominal size, | cu.m | 0.24 |
| 14 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 88.91 |
| 15 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 1.26 |
| 16 | SW0003 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels, | kg | 223.36 |
| 17 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 15.36 |
| 18 | SW00341 | Providing & fixing CRIL Sheeting with G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses-50mm, | sq.m | 16.48 |
| 19 | None | Khenthongmani, | - | - |
| 20 | EW0105 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Ordinary Soil, | cu.m | 4.7 |
| 21 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.66 |
| 22 | CW0004 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 40 mm nominal size, | cu.m | 0.24 |
| 23 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 88.91 |
| 24 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 1.26 |
| 25 | SW0003 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels, | kg | 223.36 |
| 26 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 15.36 |
| 27 | SW00341 | Providing & fixing CRIL Sheeting with G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses-50mm, | sq.m | 16.48 |
| 28 | Yelchen | |||
| 29 | EW0105 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Ordinary Soil, | cu.m | 4.7 |
| 30 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.66 |
| 31 | CW0004 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 40 mm nominal size, | cu.m | 0.24 |
| 32 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 88.91 |
| 33 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 1.26 |
| 34 | SW0003 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels, | kg | 223.36 |
| 35 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 15.36 |
| 36 | SW00341 | Providing & fixing CRIL Sheeting with G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses-50mm, | sq.m | 16.48 |