Construction of Foundation for Tower,Shelter and Solar at Bazor under Trashi yangtsi Dzongkhag Bhutan Telecom Ltd Contract Awarded
Procurement Category: Civil
Dzongkhag/Location: Trashiyangtse
Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)
Procurement Method: Open Tendering
Annual Procurement Plan: 2021
Bidding Process: Single Stage Bidding - Single Envelope
Contact Details: Cheki Wangmo Civil Engineer 17162638 BTL SJK
Status: Contract Awarded
Bidding Details
Submission Date: August 18 2021, 12:00 PM
Opening Date: August 18 2021, 02:30 PM
Prebid Date: None
Prebid Place: None
Earnest Money Deposit Details
EMD Type: Lumpsum
EMD Value: Nu. 32,300.00/-
Evaluation Details
Financial Evaluation: 100%
Agency Documents
Sl | Document | Link |
---|---|---|
1 | Compliance Sheet | Download |
2 | Integrity Pact Document | Download |
3 | Revised Tender Document | Download |
4 | Drawings | Download |
Document Prerequisites For Participation
Sl | Document |
---|---|
1 | Bid Form |
2 | CDB License |
3 | Integrity Pact Document |
4 | Tax Clearance |
5 | Trade License |
Tender Items(BOQ/BOM)
Sl | Item Code | Item Name, Additional Description/Specifications |
UoM | Qty |
---|---|---|---|---|
1 | Const. of Foundation for 30M Tower | |||
2 | CG0002 | Clearing jungle including uprooting of vegetation & trees of girth < 300mm & disposal within 50m of the site, | sq.m | 196.0 |
3 | CG0011 | Felling trees including cutting of trunks and branches, removal of roots, stacking of serviceable materials and disposal of rubbish within 50m lead - Girth 600 to 1200mm, | each | 12.0 |
4 | EW0031 | Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, | cu.m | 92.42 |
5 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 60.0 |
6 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 1.59 |
7 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 9.34 |
8 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 900.38 |
9 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 38.94 |
10 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 42.85 |
11 | Construction of Foundation for Shleter, | - | - | |
12 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 7.11 |
13 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.82 |
14 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 4.32 |
15 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 375.12 |
16 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 20.16 |
17 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 17.64 |
18 | None | Const. of Foundation of Solar, | - | - |
19 | EW0031 | Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, | cu.m | 10.56 |
20 | EW0105 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Ordinary Soil, | cu.m | 21.6 |
21 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.51 |
22 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 17.28 |
23 | SW00343 | Providing and Fixing of 65X65x6mm equal angle for support with complete Aluminium Paint, | each | 417.6 |
24 | SW00344 | P&F of flat to be welded in foundation with complete Paint, | nos | 64.8 |
25 | SW00345 | P& F of Nut and Bolts, | nos | 30.0 |