Construction of Foundation for Tower,Shelter and Solar at Bazor under Trashi yangtsi Dzongkhag Bhutan Telecom Ltd Contract Awarded


Procurement Category: Civil

Dzongkhag/Location: Trashiyangtse

Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)

Procurement Method: Open Tendering

Annual Procurement Plan: 2021

Bidding Process: Single Stage Bidding - Single Envelope

Contact Details: Cheki Wangmo Civil Engineer 17162638 BTL SJK

Status: Contract Awarded


Bidding Details

Submission Date: August 18 2021, 12:00 PM

Opening Date: August 18 2021, 02:30 PM

Prebid Date: None

Prebid Place: None

Earnest Money Deposit Details

EMD Type: Lumpsum

EMD Value: Nu. 32,300.00/-

Evaluation Details

Financial Evaluation: 100%

Agency Documents


Sl Document Link
1 Compliance Sheet Download
2 Integrity Pact Document Download
3 Revised Tender Document Download
4 Drawings Download
Document Prerequisites For Participation


Sl Document
1 Bid Form
2 CDB License
3 Integrity Pact Document
4 Tax Clearance
5 Trade License
Tender Items(BOQ/BOM)


Sl Item Code Item Name,
Additional Description/Specifications
UoM Qty
1 Const. of Foundation for 30M Tower
2 CG0002 Clearing jungle including uprooting of vegetation & trees of girth < 300mm & disposal within 50m of the site, sq.m 196.0
3 CG0011 Felling trees including cutting of trunks and branches, removal of roots, stacking of serviceable materials and disposal of rubbish within 50m lead - Girth 600 to 1200mm, each 12.0
4 EW0031 Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, cu.m 92.42
5 EW0106 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, cu.m 60.0
6 CW0008 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), cu.m 1.59
7 RC0002 Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), cu.m 9.34
8 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, kg 900.38
9 RC0093 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., sq.m 38.94
10 EW0195 Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, cu.m 42.85
11 Construction of Foundation for Shleter, - -
12 EW0106 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, cu.m 7.11
13 CW0008 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), cu.m 0.82
14 RC0002 Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), cu.m 4.32
15 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, kg 375.12
16 RC0093 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., sq.m 20.16
17 EW0195 Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, cu.m 17.64
18 None Const. of Foundation of Solar, - -
19 EW0031 Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, cu.m 10.56
20 EW0105 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Ordinary Soil, cu.m 21.6
21 CW0003 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, cu.m 1.51
22 RC0090 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., sq.m 17.28
23 SW00343 Providing and Fixing of 65X65x6mm equal angle for support with complete Aluminium Paint, each 417.6
24 SW00344 P&F of flat to be welded in foundation with complete Paint, nos 64.8
25 SW00345 P& F of Nut and Bolts, nos 30.0