Construction of Foundation for Tower and Shelter at Tokaphu Bhutan Telecom Ltd Contract Awarded


Procurement Category: Civil

Dzongkhag/Location: Samdrup Jongkhar

Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)

Procurement Method: Limited Tendering

Annual Procurement Plan: 2021

Bidding Process: Single Stage Bidding - Single Envelope

Contact Details: Cheki Wangmo 17162638

Status: Contract Awarded


Bidding Details

Submission Date: September 07 2026, 12:00 AM

Opening Date: September 06 2021, 02:30 PM

Prebid Date: None

Prebid Place: None

Earnest Money Deposit Details

EMD Type: Lumpsum

EMD Value: Nu. 6,800.00/-

Evaluation Details

Financial Evaluation: 100%

Agency Documents


Sl Document Link
1 Integrity Pact Document Download
2 Revised Tender Document Download
3 RFP Download
Document Prerequisites For Participation


Sl Document
1 Bid Form
2 CDB License
3 Integrity Pact Document
4 Tax Clearance
5 Trade License
Tender Items(BOQ/BOM)


Sl Item Code Item Name,
Additional Description/Specifications
UoM Qty
1 Tower
2 CG0002 Clearing jungle including uprooting of vegetation & trees of girth < 300mm & disposal within 50m of the site, sq.m 196.0
3 CG0011 Felling trees including cutting of trunks and branches, removal of roots, stacking of serviceable materials and disposal of rubbish within 50m lead - Girth 600 to 1200mm, each 12.0
4 EW0031 Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, cu.m 92.4
5 EW0106 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, cu.m 41.26
6 CW0008 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), cu.m 1.59
7 RC0002 Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), cu.m 6.16
8 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, kg 554.45
9 RC0093 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., sq.m 34.98
10 EW0195 Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, cu.m 42.85
11 None Shelter, - -
12 EW0106 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, cu.m 7.11
13 CW0008 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), cu.m 0.82
14 RC0002 Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), cu.m 3.17
15 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, kg 312.16
16 RC0093 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., sq.m 20.16
17 EW0195 Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, cu.m 17.64