Construction of Dg shed at Shashingpong,Bumthang Bhutan Telecom Ltd Contract Awarded
Procurement Category: Civil
Dzongkhag/Location: Bumthang
Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)
Procurement Method: Open Tendering
Annual Procurement Plan: 2022
Bidding Process: Single Stage Bidding - Single Envelope
Contact Details: Pema Wangdi (Mr.) Civil Engineering Section, Central Region, BTL. Tel: +975 2 343434 Ext. 6013 | Mob: +975 17141880| pema.wangdi2573@bt.bt Bhutan Telecom Ltd: www.bt.bt |
Status: Contract Awarded
Bidding Details
Submission Date: March 30 2022, 05:00 PM
Opening Date: March 31 2022, 02:00 PM
Prebid Date: None
Prebid Place: gelephu
Earnest Money Deposit Details
EMD Type: Lumpsum
EMD Value: Nu. 7,000.00/-
Evaluation Details
Financial Evaluation: 100%
Agency Documents
Sl | Document | Link |
---|---|---|
1 | Bid Form | Download |
2 | Integrity Pact Document | Download |
3 | Drawings | Download |
4 | RFP | Download |
Document Prerequisites For Participation
Sl | Document |
---|---|
2 | Bid Form |
6 | CDB License |
15 | Integrity Pact Document |
21 | Tax Clearance |
24 | Trade License |
Tender Items(BOQ/BOM)
Sl | Item Code | Item Name, Additional Description/Specifications |
UoM | Qty |
---|---|---|---|---|
1 | Construction of DG shed at Shashingpong | |||
2 | EW0031 | Excavation in foundation trenches or drains not exceeding 1.5m width or area 10 sq. m on plan, including dressing or ramming, disposal of surplus soil 5000m away for any lead and lifts-All kinds of soil , | cu.m | 9.45 |
3 | CW0005 | Providing and laying in position plain cement concrete 1:3:6, 20mm nominal aggregates, excluding the cost of centering and shuttering -all work upto plinth level, | cu.m | 1.26 |
4 | SM0005 | Providing and laying Random Rubble Masonry with hard stone in foundation and plinth, in Cement mortar as specified. 1:4, | cu.m | 7.64 |
5 | BW0002 | Providing and fixing second class brick work in foundation and plinth in cement mortar 1:4, | cu.m | 8.4 |
6 | RC0090 | P/F centering & shuttering (formwork) incl. strutting, propping etc & removal of formwork in foundation & plinth., | sq.m | 23.4 |
7 | CW0001 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level.1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nominal size)-flooring, | cu.m | 3.26 |
8 | WW0060 | Providing & fixing in position dressed wood work in frames of doors, windows, clerestory windows and other frames, wrought and framed mixed confier in truss, | cu.m | 5.289 |
9 | WW0030 | Providing & fixing Eaves board (225x25mm) with moulding fitted and fixed with necessary screws, | m | 16.8 |
10 | WW0132 | Providing & fixing Plywood lining with necessary nails etc. including beading complete (excluding cost of frame) 6mm, | sq.m | 18.33 |
11 | RF0001 | Providing and fixing CRIL sheet for roofing green colour with necessary screw etc complete, | sq.m | 42.0 |
12 | SW00429 | Providing and fixing door ( double panel with size of 2X2m ) with barrel bolt in lumpsum, | nos | 1.0 |
Amendment Details
Sl | ID | Date | Details | Remarks |
---|---|---|---|---|
1 | TAM22030018 | March 04 2022, 09:31 AM | Submission Date changed from 2022-03-02 17:00:00 to 2022-03-09 17:00:00 | re tender |
2 | TAM22030019 | March 04 2022, 09:31 AM | Opening Date changed from 2022-03-03 14:00:00 to 2022-03-10 14:00:00 | re tender |
3 | TAM22030032 | March 10 2022, 02:09 PM | Submission Date changed from 2022-03-09 17:00:00 to 2022-03-16 17:00:00 | extension |
4 | TAM22030033 | March 10 2022, 02:09 PM | Opening Date changed from 2022-03-10 14:00:00 to 2022-03-17 14:00:00 | extension |
5 | TAM22030076 | March 23 2022, 09:52 AM | Submission Date changed from 2022-03-16 17:00:00 to 2022-03-23 17:00:00 | extension |
6 | TAM22030077 | March 23 2022, 09:53 AM | Opening Date changed from 2022-03-17 14:00:00 to 2022-03-24 14:00:00 | extension |
7 | TAM22030079 | March 24 2022, 02:14 PM | Submission Date changed from 2022-03-23 17:00:00 to 2022-03-30 17:00:00 | extension |
8 | TAM22030080 | March 24 2022, 02:14 PM | Opening Date changed from 2022-03-24 14:00:00 to 2022-03-31 14:00:00 | extension |