Construction of RCC slab for Entrance gate at Gelephu Bhutan Telecom Ltd Contract Awarded


Procurement Category: Civil

Dzongkhag/Location: Sarpang

Goods/Services/Work Type: CON-W1-Roads and Bridges (Small)

Procurement Method: Open Tendering

Annual Procurement Plan: 2022

Bidding Process: Single Stage Bidding - Single Envelope

Contact Details: Pema Wangdi (Mr.) Civil Engineering Section, Central Region, BTL. Tel: +975 2 343434 Ext. 6013 | Mob: +975 17141880| pema.wangdi2573@bt.bt Bhutan Telecom Ltd: www.bt.bt |

Status: Contract Awarded


Bidding Details

Submission Date: May 25 2022, 09:55 AM

Opening Date: May 25 2022, 02:00 PM

Prebid Date: None

Prebid Place: None

Earnest Money Deposit Details

EMD Type: Lumpsum

EMD Value: Nu. 10,000.00/-

Evaluation Details

Financial Evaluation: 100%

Agency Documents


Sl Document Link
1 Bid Form Download
2 RFP Download
3 Integrity Pact Document Download
Document Prerequisites For Participation


Sl Document
5 Bid Form
9 CDB License
19 Integrity Pact Document
25 Tax Clearance
30 Trade License
Tender Items(BOQ/BOM)


Sl Item Code Item Name,
Additional Description/Specifications
UoM Qty
1 Condtruction of RCC slab
2 EW0002 Surface dressing of ground, including removal of vegetations and inequalities < 150mm deep, disposal of rubbish within 50m lead and 1.5m lifts - Hard Soil, sq.m 49.5
3 EW0031 Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, cu.m 3.2
4 EW0106 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, cu.m 17.32
5 CW0003 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, cu.m 1.65
6 RC0002 Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), cu.m 16.75
7 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, kg 2987.7
8 RC0090 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., sq.m 15.3
9 RW0035 Filling of trenches, sides of foundations, walls, etc including filter material (600mm wide) with 100 to 200mm stones wherever applicable including filling with selected suitable excavated material in layer not exceeding 200mm in depth (compacted), consolidating each layer with power roller or portable compactor, watering etc. within 50m lead, cu.m 111.32
Amendment Details


Sl ID Date Details Remarks
1 TAM22050020 May 25 2022, 09:25 AM Submission Date changed from 2022-05-24 17:00:00 to 2022-05-25 09:35:00 emd submission
2 TAM22050022 May 25 2022, 09:42 AM Submission Date changed from 2022-05-25 09:35:00 to 2022-05-25 09:55:00 EMD submission