Construction of tower, shelter, solar foundation and fencing at Rezor Bhutan Telecom Ltd Being processed


Procurement Category: Civil

Dzongkhag/Location: Samdrup Jongkhar

Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)

Procurement Method: Open Tendering

Annual Procurement Plan: 2022

Bidding Process: Single Stage Bidding - Single Envelope

Contact Details: Sonam Zangpo 17123370

Status: Being processed


Bidding Details

Submission Date: September 01 2022, 04:00 PM

Opening Date: September 02 2022, 02:00 PM

Prebid Date: None

Prebid Place: None

Earnest Money Deposit Details

EMD Type: Lumpsum

EMD Value: Nu. 32,000.00/-

Evaluation Details

Financial Evaluation: 100%

Agency Documents


Sl Document Link
24 Integrity Pact Document Download
28 RFP Download
46 Bid Form Download
Document Prerequisites For Participation


Sl Document
5 Bid Form
10 CDB License
30 Integrity Pact Document
37 Tax Clearance
48 Trade License
Tender Items(BOQ/BOM)


Sl Item Code Item Name,
Additional Description/Specifications
UoM Qty
1 Tower
2 CG0002 Clearing jungle including uprooting of vegetation & trees of girth < 300mm & disposal within 50m of the site, sq.m 400.0
3 CG0011 Felling trees including cutting of trunks and branches, removal of roots, stacking of serviceable materials and disposal of rubbish within 50m lead - Girth 600 to 1200mm, each 28.0
4 EW0031 Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, cu.m 154.0
5 EW0106 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, cu.m 60.0
6 CW0008 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), cu.m 1.59
7 RC0002 Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), cu.m 6.57
8 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, kg 750.44
9 RC0093 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., sq.m 38.94
10 EW0195 Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, cu.m 42.85
11 EW0107 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lift - Ordinary rock with or without blasting, cu.m 24.0
12 None Shelter, - -
13 EW0106 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, cu.m 17.64
14 CW0008 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), cu.m 0.82
15 RC0002 Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), cu.m 3.17
16 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, kg 312.6
17 RC0093 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., sq.m 20.16
18 EW0195 Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, cu.m 17.64
19 None Chainlink fencing, - -
20 EW0105 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Ordinary Soil, cu.m 22.87
21 CW0003 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, cu.m 5.62
22 SM0005 Providing & laying Random Rubble Masonry with hard stone in foundation & plinth - In cement mortar 1:4, cu.m 36.4
23 SW0011 Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and appl. priming coat of red lead paint - In Tees, angles and channels, kg 1301.42
24 RW0209 Providing & fixing G.I chain-link mesh including fixing of post or struts, G.I staples (excluding the cost of posts/struts, earthwork, concrete etc.) - 4mm (8 SWG) x 50mm, sq.m 153.0
25 SW0011 Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and appl. priming coat of red lead paint - In Tees, angles and channels, kg 134.57
26 CW0011 Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:5:10 (1 cement : 5 sand : 10 graded crushed stone 40 mm nominal size), cu.m 3.56
27 RC0003 Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size), cu.m 1.79
28 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, kg 30.8
29 RC0090 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., sq.m 24.0
30 SW00523 P/Fixing concertina wire around chainlink fencing of two layers @150mm c/c, m 200.0
31 None Solar foundation, - -
32 EW0106 Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, cu.m 5.76
33 RC0002 Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), cu.m 4.48
34 RC0083 Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, kg 281.52
35 RC0093 Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., sq.m 11.2
36 EW0195 Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, cu.m 1.12