Construction of DG Shed with Platform Under ER Bhutan Telecom Ltd Being processed
Procurement Category: Civil
Dzongkhag/Location: Samdrup Jongkhar
Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)
Procurement Method: Open Tendering
Annual Procurement Plan: 2023
Bidding Process: Single Stage Bidding - Single Envelope
Contact Details: Sonam Zangpo 17123370
Status: Being processed
Bidding Details
Submission Date: July 13 2023, 02:00 PM
Opening Date: July 14 2023, 02:30 AM
Prebid Date: None
Prebid Place: None
Earnest Money Deposit Details
EMD Type: Lumpsum
EMD Value: Nu. 14,000.00/-
Evaluation Details
Financial Evaluation: 100%
Agency Documents
Sl | Document | Link |
---|---|---|
27 | Integrity Pact Document | Download |
33 | RFP | Download |
54 | Bid Form | Download |
Document Prerequisites For Participation
Sl | Document |
---|---|
6 | Bid Form |
11 | CDB License |
32 | Integrity Pact Document |
41 | Tax Clearance |
53 | Trade License |
Tender Items(BOQ/BOM)
Sl | Item Code | Item Name, Additional Description/Specifications |
UoM | Qty |
---|---|---|---|---|
1 | DG SHED AT TOKAPHU (SJK) | |||
2 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.78 |
3 | SM0072 | Providing and laying Hand packed stone filling or soling with stones, | cu.m | 0.79 |
4 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.39 |
5 | RC0003 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size), | cu.m | 0.38 |
6 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 97.9 |
7 | SW0011 | Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and appl. priming coat of red lead paint - In Tees, angles and channels, | kg | 207.31 |
8 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 8.79 |
9 | RF0003 | Providing & fixing Pre Painted Steel Corrugated Roofing sheets, including bolts, hooks and nuts 8mm dia. with bitumen and G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses., | sq.m | 14.22 |
10 | PT0055 | Providing and applying finishing coats - Aluminium paint, two coats on new work, | sq.m | 7.4 |
11 | None | WANGPHU DG SHED , | - | - |
12 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.78 |
13 | SM0072 | Providing and laying Hand packed stone filling or soling with stones, | cu.m | 0.79 |
14 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.39 |
15 | RC0003 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size), | cu.m | 0.38 |
16 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 97.9 |
17 | SW0011 | Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and appl. priming coat of red lead paint - In Tees, angles and channels, | kg | 207.31 |
18 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 8.79 |
19 | RF0003 | Providing & fixing Pre Painted Steel Corrugated Roofing sheets, including bolts, hooks and nuts 8mm dia. with bitumen and G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses., | sq.m | 14.22 |
20 | PT0055 | Providing and applying finishing coats - Aluminium paint, two coats on new work, | sq.m | 7.4 |
21 | None | DG SHED AT KHALONG, TASHIGANG, | - | - |
22 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.78 |
23 | SM0072 | Providing and laying Hand packed stone filling or soling with stones, | cu.m | 0.79 |
24 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.39 |
25 | RC0003 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size), | cu.m | 0.38 |
26 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 97.9 |
27 | SW0011 | Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and appl. priming coat of red lead paint - In Tees, angles and channels, | kg | 207.31 |
28 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 8.79 |
29 | RF0003 | Providing & fixing Pre Painted Steel Corrugated Roofing sheets, including bolts, hooks and nuts 8mm dia. with bitumen and G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses., | sq.m | 14.22 |
30 | PT0055 | Providing and applying finishing coats - Aluminium paint, two coats on new work, | sq.m | 7.4 |
31 | None | DG SHED AT KHALING EXCHANGE, | - | - |
32 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.78 |
33 | SM0072 | Providing and laying Hand packed stone filling or soling with stones, | cu.m | 0.79 |
34 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.39 |
35 | RC0003 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size), | cu.m | 0.38 |
36 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 97.9 |
37 | SW0011 | Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and appl. priming coat of red lead paint - In Tees, angles and channels, | kg | 207.31 |
38 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 8.79 |
39 | RF0003 | Providing & fixing Pre Painted Steel Corrugated Roofing sheets, including bolts, hooks and nuts 8mm dia. with bitumen and G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses., | sq.m | 14.22 |
40 | PT0055 | Providing and applying finishing coats - Aluminium paint, two coats on new work, | sq.m | 7.4 |
41 | None | DG SHED AT JANGSA, | - | - |
42 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.78 |
43 | SM0072 | Providing and laying Hand packed stone filling or soling with stones, | cu.m | 0.79 |
44 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.39 |
45 | RC0003 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size), | cu.m | 0.38 |
46 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 97.9 |
47 | SW0011 | Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and appl. priming coat of red lead paint - In Tees, angles and channels, | kg | 207.31 |
48 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 8.79 |
49 | RF0003 | Providing & fixing Pre Painted Steel Corrugated Roofing sheets, including bolts, hooks and nuts 8mm dia. with bitumen and G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses., | sq.m | 14.22 |
50 | PT0055 | Providing and applying finishing coats - Aluminium paint, two coats on new work, | sq.m | 7.4 |
51 | None | DG SHED AT BAINANGZOR MONGAR, | - | - |
52 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.78 |
53 | SM0072 | Providing and laying Hand packed stone filling or soling with stones, | cu.m | 0.79 |
54 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.39 |
55 | RC0003 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size), | cu.m | 0.38 |
56 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 97.9 |
57 | SW0011 | Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and appl. priming coat of red lead paint - In Tees, angles and channels, | kg | 207.31 |
58 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 8.79 |
59 | RF0003 | Providing & fixing Pre Painted Steel Corrugated Roofing sheets, including bolts, hooks and nuts 8mm dia. with bitumen and G.I limpet washers filled with white lead for connection, excluding the cost of purlins, rafter and trusses., | sq.m | 14.22 |
60 | PT0055 | Providing and applying finishing coats - Aluminium paint, two coats on new work, | sq.m | 7.4 |
61 | EW0031 | Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, | cu.m | 6.0 |
Amendment Details
Sl | ID | Date | Details | Remarks |
---|---|---|---|---|
1 | TAM23070018 | July 07 2023, 02:46 PM | Submission Date changed from 2023-07-06 16:00:00 to 2023-07-13 14:00:00 | Extension |
2 | TAM23070019 | July 07 2023, 02:47 PM | Opening Date changed from 2023-07-07 14:30:00 to 2023-07-14 02:30:00 | Extension |