Construction of 15m monopole foundation under Thimphu PC Bhutan Telecom Ltd Live Participate
Procurement Category: Civil
Dzongkhag/Location: Thimphu
Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)
Procurement Method: Open Tendering
Annual Procurement Plan: 2025
Bidding Process: Single Stage Bidding - Single Envelope
Contact Details: Pema Wangdi (Mr.) Civil Engineering Section, Western Region, BTL. Tel: +975 2 343434 Ext. 4027 | Mob: +975 17141880| pema.wangdi2573@bt.bt Bhutan Telecom Ltd: www.bt.bt |
Status: Live
Bidding Details
Submission Date: January 08 2025, 12:30 PM
Opening Date: January 08 2025, 02:30 PM
Prebid Date: None
Prebid Place: None
Earnest Money Deposit Details
EMD Type: Lumpsum
EMD Value: Nu. 18,000.00/-
Evaluation Details
Financial Evaluation: 100%
Agency Documents
Sl | Document | Link |
---|---|---|
1 | Bid Form | Download |
2 | Integrity Pact Document | Download |
3 | RFP | Download |
4 | Drawings | Download |
Document Prerequisites For Participation
Sl | Document |
---|---|
7 | Bid Form |
16 | CDB License |
44 | Integrity Pact Document |
56 | Tax Clearance |
76 | Trade License |
Tender Items(BOQ/BOM)
Sl | Item Code | Item Name, Additional Description/Specifications |
UoM | Qty |
---|---|---|---|---|
1 | 15m monoopole foundation at Above rinchen School | |||
2 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 15.14 |
3 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.73 |
4 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 4.18 |
5 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 485.83 |
6 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 39.45 |
7 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 9.03 |
8 | SW00449 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels - Ms angles 50X50X5mm-need to be paint with aluminium for cabinet stand, | kg | 65.0 |
9 | Services00467 | P/laying 25 mm HDPE for water drain out , | each | 1.0 |
10 | None | changdiphu Grid Apartment , | - | - |
11 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 15.14 |
12 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.73 |
13 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 4.18 |
14 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 485.83 |
15 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 39.45 |
16 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 9.03 |
17 | SW00449 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels - Ms angles 50X50X5mm-need to be paint with aluminium , | kg | 65.0 |
18 | Services00467 | P/laying 25 mm HDPE for water drain out , | each | 1.0 |
19 | None | Dochula REsort, | - | - |
20 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 15.14 |
21 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.73 |
22 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 4.18 |
23 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 485.83 |
24 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 39.45 |
25 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 9.03 |
26 | SW00449 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels - Ms angles 50X50X5mm-need to be paint with aluminium , | kg | 65.0 |
27 | Services00467 | P/laying 25 mm HDPE for water drain out , | each | 1.0 |
28 | None | Fly over Bridge, | - | - |
29 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 15.14 |
30 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.73 |
31 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 4.18 |
32 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 485.83 |
33 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 39.45 |
34 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 9.03 |
35 | SW00449 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels - Ms angles 50X50X5mm-need to be paint with aluminium , | kg | 65.0 |
36 | Services00467 | P/laying 25 mm HDPE for water drain out , | each | 1.0 |
37 | None | Jangdikha, | - | - |
38 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 15.14 |
39 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.73 |
40 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 4.18 |
41 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 485.83 |
42 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 39.45 |
43 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 9.03 |
44 | SW00449 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels - Ms angles 50X50X5mm-need to be paint with aluminium , | kg | 65.0 |
45 | Services00467 | P/laying 25 mm HDPE for water drain out , | each | 1.0 |
46 | None | Rinchen kuenphen school, | - | - |
47 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 15.14 |
48 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.73 |
49 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 4.18 |
50 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 485.83 |
51 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 39.45 |
52 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 9.03 |
53 | SW00449 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels - Ms angles 50X50X5mm-need to be paint with aluminium , | kg | 65.0 |
54 | Services00467 | P/laying 25 mm HDPE for water drain out , | each | 1.0 |
55 | None | Simtokha, | - | - |
56 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 15.14 |
57 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.73 |
58 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 4.18 |
59 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 485.83 |
60 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 39.45 |
61 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 9.03 |
62 | SW00449 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels - Ms angles 50X50X5mm-need to be paint with aluminium , | kg | 65.0 |
63 | Services00467 | P/laying 25 mm HDPE for water drain out , | each | 1.0 |
64 | None | Talakha VVIP, | - | - |
65 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 15.14 |
66 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.73 |
67 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 4.18 |
68 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 485.83 |
69 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 39.45 |
70 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 9.03 |
71 | SW00449 | Steel work in single section including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles and channels - Ms angles 50X50X5mm-need to be paint with aluminium , | kg | 65.0 |
72 | Services00467 | P/laying 25 mm HDPE for water drain out , | each | 1.0 |