Construction of 4.00 km Forest Road at Rodungla Forest Management Unit Natural Resource Development Corporation Limited Live Participate


Procurement Category: Civil

Dzongkhag/Location: Bumthang

Goods/Services/Work Type: CON-W1-Roads and Bridges (Medium)

Procurement Method: Open Tendering

Annual Procurement Plan: 2025

Bidding Process: Single Stage Bidding - Single Envelope

Contact Details: Bishal Subba Civil Engineer 17940403

Status: Live


Bidding Details

Submission Date: May 08 2025, 06:00 PM

Opening Date: May 09 2025, 02:30 PM

Prebid Date: None

Prebid Place: None

Earnest Money Deposit Details

EMD Type: Lumpsum

EMD Value: Nu. 209,409.88/-

Evaluation Details

Financial Evaluation: 100%

Agency Documents


Sl Document Link
2 Bid Data Sheet Download
3 Special Conditions of the Contract (SCC) Download
4 General Conditions of Contract (GCC) Download
5 Integrity Pact Document Download
6 Bid Submission Form Download
7 Bill of Quantities Download
8 Drawings Download
9 Drawings Download
10 Drawings Download
11 Drawings Download
12 Evaluation Criteria Download
13 Documents required (Equipment and Manpower) Download
Document Prerequisites For Participation


Sl Document
1 Bid Submission Form
2 CDB License
3 Equipment Documents
4 Integrity Pact Document
5 Manpower Documents
6 Tax Clearance
7 Trade License
Tender Items(BOQ/BOM)


Sl Item Code Item Name,
Additional Description/Specifications
UoM Qty
1 CG0002 Clearing jungle including up-rooting of vegetation and felling of trees of girth greater than 300mm & stacking within 50m of the site. ,
The road alignment timber has to be stacked and used for construction of culverts and cross drains and timber can be extracted with NRDCL approved rates
sq.m 40000.0
2 NRDCL00001 Excavation of 4000m (4.00 km) road formation/trace/box cutting in both soil and rock strata using an excavator, including separate stacking of excavated soil, rock, and sandstone materials within 50 meters for reuse. The excavated material shall be transported over a distance of up to 1000 meters, regardless of station markings. All disposed material shall be leveled and neatly dressed. The general formation width shall be 6 meters; however, increased widths shall be adopted at zigs, sharp ridges, and valley sections as instructed by the site supervisor. Cutting width shall be carried out strictly as per the drawings and site instructions.,
Please enter lumpsum amount for formation cutting of 1.00 km road. the rate shall include for both rock as well as soil portion. it is advised to visit the site prior to bidding and have a clear understanding of the site.
LS 1.0
3 NRDCL00002 Complete construction of log culverts (4m x 1m) as per the drawings, using suitable road alignment timber with diameter not less than 500 mm. The work includes excavation for foundations, placement and alignment of logs as specified in the drawings including royalty if required, and all associated works required to complete the structure in accordance with design and instructions.,
The log culverts have to made using the timber from road alignment.
no 11
4 NRDCL00003 Complete construction of cross drains (4m) as per the drawings after every 40m interval, using suitable road alignment timber with diameter not less than 500 mm. The work includes excavation for foundations, placement and alignment of logs as specified in the drawings including royalty if required, and all associated works required to complete the structure in accordance with design and instructions.,
the logs from road alignment has to be used constructing cross drains.
no 100
5 RW0030 Construction of embankment by laying dry earth in horizontal layers not exceeding 150mm in depth (compacted), including watering,power rolling, dressing and preparation of site with selected excavated earth within 500 m lead,
Width = 3 m
Height = 0.3 m 
Length = 4 km or 4000m
cu.m 3600.0
6 EW0047 Earth work in excavation for side drain over areas using Excavator, exceeding 300mm in depth, 1.5m in width as well as 10 sq.m in area on plan, including dressing, levelling and disposal of excavated earth, lead up to 50m and lift up to 1.5m in all types of soil and rock both. The rate shall be applicable for both rock and soil portion. ,
Side drain along road with 1m width and 1m depth 1000m long (4000 x 1 x 1)
cu.m 4000.0
7 SM0073 Providing and laying Hammer dressed stone edging 150 x 250 mm with stones including excavation, refilling and disposal of surplus earth within 30 m lead, m 8000.0
8 SM0072 Providing and laying Hand packed stone filling or soling with stones ,
Width = 3.2 m
Height = 0.15 m
cu.m 1920.0
9 RW0123 Consolidation of road surface with roller, and making good the undulation with earth and re-rolling the surface,
Length =4000m
Width = 3.5 m (including edging and soling)
sq.m 14000.0