Construction of 40meter tower foundation at Chengbari under Samtse P.C(Package 2) Bhutan Telecom Ltd Being processed
Procurement Category: Civil
Dzongkhag/Location: Samtse
Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)
Procurement Method: Open Tendering
Annual Procurement Plan: 2025
Bidding Process: Single Stage Bidding - Single Envelope
Contact Details: Khem Raj Ghalley Civil Engineer 17151425
Status: Being processed
Bidding Details
Submission Date: October 28 2025, 12:00 PM
Opening Date: October 28 2025, 02:00 PM
Prebid Date: None
Prebid Place: None
Earnest Money Deposit Details
EMD Type: Lumpsum
EMD Value: Nu. 13,400.00/-
Evaluation Details
Financial Evaluation: 100%
Agency Documents
| Sl | Document | Link |
|---|---|---|
| 1 | Bid Form | Download |
| 2 | Integrity Pact Document | Download |
| 3 | Drawings | Download |
| 4 | Drawing 02 | Download |
| 5 | RFP | Download |
Document Prerequisites For Participation
| Sl | Document |
|---|---|
| 10 | Bid Form |
| 19 | CDB License |
| 61 | Integrity Pact Document |
| 72 | RFP |
| 78 | Tax Clearance |
| 107 | Trade License |
Tender Items(BOQ/BOM)
| Sl | Item Code | Item Name, Additional Description/Specifications |
UoM | Qty |
|---|---|---|---|---|
| 1 | Construction of 40meter tower foundation at Chengbari under Samtse P.C(Package 2) | |||
| 2 | EW0002 | Surface dressing of ground, including removal of vegetations and inequalities < 150mm deep, disposal of rubbish within 50m lead and 1.5m lifts - Hard Soil, | sq.m | 225.0 |
| 3 | EW0031 | Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, | cu.m | 22.5 |
| 4 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 144.66 |
| 5 | EW0107 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lift - Ordinary rock with or without blasting, | cu.m | 143.34 |
| 6 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.73 |
| 7 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 4.1 |
| 8 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 24.06 |
| 9 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 1944.72 |
| 10 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 89.82 |
| 11 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 112.0 |