Construction of tower and cabinet foundation at Pugli under Samtse P.C(package 3) Bhutan Telecom Ltd Live Participate
Procurement Category: Civil
Dzongkhag/Location: Samtse
Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)
Procurement Method: Open Tendering
Annual Procurement Plan: 2026
Bidding Process: Single Stage Bidding - Single Envelope
Contact Details: Mr. Khem Raj Ghalley Civil Engineer 17151425
Status: Live
Bidding Details
Submission Date: January 26 2026, 12:00 PM
Opening Date: January 26 2026, 02:00 PM
Prebid Date: None
Prebid Place: None
Earnest Money Deposit Details
EMD Type: Lumpsum
EMD Value: Nu. 35,650.00/-
Evaluation Details
Financial Evaluation: 100%
Agency Documents
| Sl | Document | Link |
|---|---|---|
| 1 | Drawings | Download |
| 2 | Drawing 02 | Download |
| 3 | Drawings | Download |
| 4 | Drawing 02 | Download |
| 5 | Drawing 02 | Download |
| 6 | Bid Form | Download |
| 7 | Integrity Pact Document | Download |
| 8 | RFP | Download |
Document Prerequisites For Participation
| Sl | Document |
|---|---|
| 10 | Bid Form |
| 19 | CDB License |
| 61 | Integrity Pact Document |
| 72 | RFP |
| 78 | Tax Clearance |
| 107 | Trade License |
Tender Items(BOQ/BOM)
| Sl | Item Code | Item Name, Additional Description/Specifications |
UoM | Qty |
|---|---|---|---|---|
| 1 | Construction of 40mtr tower foundation with chain link fencing at Pugli | |||
| 2 | CG0002 | Clearing jungle including uprooting of vegetation & trees of girth < 300mm & disposal within 50m of the site, | sq.m | 225.0 |
| 3 | EW0002 | Surface dressing of ground, including removal of vegetations and inequalities < 150mm deep, disposal of rubbish within 50m lead and 1.5m lifts - Hard Soil, | sq.m | 225.0 |
| 4 | EW0031 | Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including disposal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil, | cu.m | 180.0 |
| 5 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 144.66 |
| 6 | EW0107 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lift - Ordinary rock with or without blasting, | cu.m | 144.66 |
| 7 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 4.1 |
| 8 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 24.68 |
| 9 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 2144.94 |
| 10 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 84.6 |
| 11 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 112.0 |
| 12 | None | Construction of chain link fencing at Pugli tower, | - | - |
| 13 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 39.48 |
| 14 | SM0072 | Providing and laying Hand packed stone filling or soling with stones, | cu.m | 3.96 |
| 15 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 4.79 |
| 16 | CW0011 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:5:10 (1 cement : 5 sand : 10 graded crushed stone 40 mm nominal size), | cu.m | 2.48 |
| 17 | SM0005 | Providing & laying Random Rubble Masonry with hard stone in foundation & plinth - In cement mortar 1:4, | cu.m | 26.54 |
| 18 | SW0011 | Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and appl. priming coat of red lead paint - In Tees, angles and channels, | kg | 922.01 |
| 19 | SW0021 | Steel work welded, in built up sections, trusses, frame-works including cutting, hoisting, fixing and appl. priming coat of red - In Tees, angles and channels, | kg | 140.21 |
| 20 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 0.89 |
| 21 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 101.75 |
| 22 | RW0209 | Providing & fixing G.I chain-link mesh including fixing of post or struts, G.I staples (excluding the cost of posts/struts, earthwork, concrete etc.) - 4mm (8 SWG) x 50mm, | sq.m | 111.6 |
| 23 | RC0093 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts etc., | sq.m | 37.37 |
| 24 | None | Construction of 15mtr monopole foundation at Dzongsar school, | - | - |
| 25 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 19.84 |
| 26 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.35 |
| 27 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.94 |
| 28 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 3.48 |
| 29 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 497.4 |
| 30 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 16.42 |
| 31 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 13.69 |
| 32 | PO0370 | Providing & fixing P.V.C soil waste and vent pipes, single or double socketed, including pipe clip complete (excluding the cost of PVC fittings) - 75mm dia, | m | 1.2 |
| 33 | None | Construction of 15mtr monopole foundation at Sukerety , | - | - |
| 34 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 19.84 |
| 35 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.35 |
| 36 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.94 |
| 37 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 3.48 |
| 38 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 497.4 |
| 39 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 16.42 |
| 40 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 14.81 |
| 41 | PO0370 | Providing & fixing P.V.C soil waste and vent pipes, single or double socketed, including pipe clip complete (excluding the cost of PVC fittings) - 75mm dia, | m | 1.2 |
| 42 | None | Construction of 20mtr monopole foundation at Samtse jail, | - | - |
| 43 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 15.03 |
| 44 | CW0008 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 40 mm nominal size), | cu.m | 0.35 |
| 45 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.94 |
| 46 | RC0002 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size), | cu.m | 3.52 |
| 47 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 366.17 |
| 48 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 16.78 |
| 49 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 13.69 |
| 50 | PO0370 | Providing & fixing P.V.C soil waste and vent pipes, single or double socketed, including pipe clip complete (excluding the cost of PVC fittings) - 75mm dia, | m | 1.2 |
| 51 | None | Construction of cabinet foundation at Belpoteng at sibsoo, | - | - |
| 52 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.18 |
| 53 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.94 |
| 54 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 6.78 |
| 55 | None | Construction of cabinet foundation at Lamitar, | - | - |
| 56 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.18 |
| 57 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.94 |
| 58 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 6.78 |
| 59 | None | Construction of cabinet foundation at Ugyentse, | - | - |
| 60 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.18 |
| 61 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.94 |
| 62 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 6.78 |
| 63 | None | Construction of cabinet foundation at Changju,Tendu, | - | - |
| 64 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.18 |
| 65 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.94 |
| 66 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 6.78 |
| 67 | None | Construction of cabinet foundation at Yangtsina,Dorokha, | - | - |
| 68 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.18 |
| 69 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.94 |
| 70 | RC0090 | Providing & fixing centering and shuttering (formwork), including strutting, propping etc. and removal of formwork - Foundation and plinth etc., | sq.m | 6.78 |
| 71 | None | Construction of cabinet foundation at Dyna Industrial, | - | - |
| 72 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 1.18 |
| 73 | CW0003 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:2:4 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size, | cu.m | 1.94 |