Construction of 15 and 20m Monopole foundation Bhutan Telecom Ltd Being processed
Procurement Category: Civil
Dzongkhag/Location: Sarpang
Goods/Services/Work Type: CON-W4-Power and Telecommunications Works (Small)
Procurement Method: Limited Tendering
Annual Procurement Plan: 2026
Bidding Process: Single Stage Bidding - Single Envelope
Contact Details: Tashi Wangdi, 17113305
Status: Being processed
Bidding Details
Submission Date: September 28 2026, 12:00 PM
Opening Date: September 28 2026, 02:30 PM
Prebid Date: None
Prebid Place: None
Evaluation Details
Financial Evaluation: 100%
Document Prerequisites For Participation
| Sl | Document |
|---|---|
| 1 | Bid Form |
| 2 | Integrity Pact Document |
Tender Items(BOQ/BOM)
| Sl | Item Code | Item Name, Additional Description/Specifications |
UoM | Qty |
|---|---|---|---|---|
| 1 | Construction of 15m monopole tower | |||
| 2 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 13.12 |
| 3 | CW0009 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 50 mm nominal size), | cu.m | 0.36 |
| 4 | RC0003 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size), | cu.m | 5.18 |
| 5 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 337.1 |
| 6 | RC0111 | Centering and shuttering using shuttering ply Columns, pillars, post, struts, etc., | sq.m | 13.13 |
| 7 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 8.56 |
| 8 | None | 20m monopole foundation, | - | - |
| 9 | EW0106 | Excavation in foundation trenches or drains not exceeding 1.5m in width or area 10 sq.m on plan, including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lif - Hard Soil, | cu.m | 13.12 |
| 10 | CW0009 | Providing and laying in position plain cement concrete excluding the cost of centering and shuttering - All work upto plinth level. - 1:4:8 (1 cement : 4 sand : 8 graded crushed stone 50 mm nominal size), | cu.m | 0.36 |
| 11 | RC0003 | Providing & laying in position reinforced cement concrete excluding the cost of centering, shuttering and reinforcement - all work upto plinth level - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size), | cu.m | 5.18 |
| 12 | RC0083 | Providing & fixing Thermo-Mechanically Treated reinforcement bar (Yield Strength 500 MPa) for R.C.C work including cutting, bending, binding and placing in position complete, | kg | 337.1 |
| 13 | RC0111 | Centering and shuttering using shuttering ply Columns, pillars, post, struts, etc., | sq.m | 13.13 |
| 14 | EW0195 | Filling of trenches, sides of foundations etc. in layers <200mm using selected excavated earth, ramming etc. within lead 50 m & lift 1.5m, | cu.m | 8.56 |
Amendment Details
| Sl | ID | Date | Details | Remarks |
|---|---|---|---|---|
| 1 | TAM26090001 | September 18 2026, 03:56 PM | Total Estimated changed from 0 to 161701.61 | amended as estimate amount is missing |